South Korea's draft rule would exempt AI data centers up to 50 MW from grid review outside the Seoul area

South Korea's Ministry of Science and ICT on Nov. 20 published draft decrees for its AI data center special act. AI data centers built outside the Seoul metropolitan area (Seoul, Incheon and Gyeonggi Province) would skip the national grid impact review under the draft if their contracted power is 50 megawatts or less. Today, any business planning to draw 10 MW or more in a designated area must go through that review. Comments are open until Dec. 30, and the rules are set to take effect with the law on March 10, 2027.

Written by AI
Report an error
Two horizontal bands on a 0 to 100 MW scale, titled 'Grid review: from 10 MW to above 50 MW'. Top band, today's rule for any large power user: review at 10 MW or more. Bottom band, the draft rule for AI data centers outside the Seoul area: exempt up to 50 MW, review above 50 MW, in blue.
Where a grid impact review kicks in: 10 MW in designated areas under today's rule, and above 50 MW for AI data centers outside the Seoul area under the draft decree. · Graphic: HOLT NEWS · Data: Ministry of Science and ICT, Korea Law Information Center

The 40 MW question

Suppose a company wants to build a 40-megawatt AI data center in South Korea outside the Seoul metropolitan area, which covers Seoul, Incheon and Gyeonggi Province. If the site is in a designated area, today's rules require a grid impact assessmentA review, before a large power user connects, of whether the local grid can carry the new load. before it applies for permits: a review of whether the local power network can handle a big new load. Under draft decrees published on Nov. 20 by the Ministry of Science and ICT, it would skip that step if the rule is finalized as written.

The decrees flesh out the Special Act on the Promotion of the AI Data Center Industry, which was promulgated on June 9, 2026 and takes effect on March 10, 2027. Comments are open until Dec. 30, and a public hearing is set for Dec. 9 in Seoul.

From 10 MW to 50 MW

The current threshold sits in Article 25 of the enforcement decree of the Distributed Energy Act. In areas designated by the Ministry of Climate, Energy and Environment, any business planning to draw 10 MW or more must be assessed. The report is due three months before the business applies for permits, and the government has three months after receiving it to notify the outcome.

Article 17 of the draft would exempt new, expanded or converted AI data centers outside the Seoul metropolitan area with contracted power of 50 MW or less. Contracted power is the maximum load a customer agrees with the utility, not actual use. That moves the line five times higher. A 50 MW site running flat out for all 8,760 hours of a year would use 438 gigawatt-hours; a 10 MW site would use 87.6 GWh. Actual use depends on how busy the servers are.

There is a precedent. Article 26 of the same decree already allows exemptions for projects in national strategic high-tech industries. AI data centers are not named there; the new act sets a threshold of its own.

What counts as an AI data center

To get the exemption, a site must first qualify. Article 3 of the draft measures AI equipment power, the electricity designed to feed racks of GPUs, NPUs and other AI accelerators. A site qualifies with at least 250 kilowatts of AI equipment power that makes up 50% or more of its total IT power, or with at least 5 MW of AI equipment power. The ratio and size figures are set by ministry notice.

Take a site with 2 MW of IT power. If 1.2 MW goes to AI racks, the share is 60% and it qualifies; with 0.9 MW, the share is 45% and it misses the ratio test. There is an efficiency test too: total facility power divided by IT power must be 1.5 or lower at the design stage, which the ministry says works out to roughly 1.3 to 1.4 in operation. Sites also need cooling, backup power, fire safety and security systems. Colocation sites that rent out space and power for other companies' AI racks are covered.

Who saves time, who carries the cost

Developers gain time and space. Skipping the review can shorten the permit schedule, and under a bundled-permit track, if a related agency does not reply within 10 days, the process moves ahead on the documents already filed. Required on-site parking can be cut by 20%, and local ordinances can ease it further, to as little as half the standard. Server rooms can also be left out of the floor area used to set Korea's mandatory public-art spending for new buildings: all of it outside the Seoul area, half inside it.

What remains is the grid. Skipping the review does not make a big new load any smaller. The government said it weighed industry demands against the effect of large AI data centers on regional networks and settled on 50 MW. The ministries also noted that raising the line to 100 MW would still leave most gigawatt-scale projects outside it, so they agreed on two parallel measures instead.

The draft also targets developers that file plans and never build. A company filing a construction notice must set a construction start date within one year of filing, a step meant to stop firms from locking in the exemption without breaking ground. In short, developers would save paperwork and waiting time; the job of expanding regional grids stays.

Two related measures

Two separate measures, to be set by the climate ministry through a notice and a work manual rather than the decree, apply regardless of size. An 'AIDC fast track' puts reviews for mega projects and bundled-permit data centers at the front of the queue. Inside AI data center zones, which local governments apply for, data centers would skip the non-technical part of the review and face only the technical part, though the scoring for power demand may be adjusted.

In those zones, central and local governments could build or fund roads, heat supply and energy storage, waste-heat reuse, high-speed networks and facilities for nearby residents, on top of power and water. The ministry has 90 days to review a zone application before the National AI Strategy Committee decides. Numbers can still change after comments close on Dec. 30, so developers should check the contracted-power threshold again in the final decree.